Mangaluru-Bengaluru Rail Services Disrupted By Ghat Landslip: Which Trains Have Been Cancelled Or Diverted?

Rail travel between coastal Karnataka and Bengaluru faced a major breakdown after soil and debris covered the track between Yedakumari and Shrivagilu in Hassan district. The landslip, reported around 8:45 pm on August 1, forced South Western Railway to stop trains, cancel scheduled services, and send several long-distance trains through Kerala or Goa.

The disruption has affected passengers heading towards Bengaluru, Mangaluru, Karwar, Kozhikode, Murdeshwar, Vijayapura and Hubballi. With heavy rain continuing across the ghat stretch, railway officials have not announced a firm time for full restoration. Passengers have been asked to verify their train status before leaving home.

What Happened On The Mangaluru-Bengaluru Railway Route?

The blocked portion lies on the steep Sakleshpur-Subrahmanya Road section, one of Karnataka’s toughest railway corridors during the monsoon. A goods train loco pilot noticed debris on the track and alerted railway control. The train was taken back towards Subrahmanya Road, while a material train carrying equipment and workers was sent to the site.

According to a railway official cited in the latest Mangaluru rail disruption report, the ghat region received about 245 to 250 mm of rain on Saturday night. Restoration teams must clear the debris, examine the rails, and inspect traction, signalling and communication systems before passenger services can restart safely.

Which Trains Have Been Cancelled Or Diverted?

South Western Railway first cancelled five journeys scheduled for August 2. A later bulletin added three cancellations for August 3. The railway’s official cancellation notice and official diversion update remain useful for passengers tracking fresh changes.

The main changes announced were:

  • August 2 cancellations included Train 16595 KSR Bengaluru-Karwar Panchaganga Express, 16596 Karwar-KSR Bengaluru Panchaganga Express, 56920 Vijayapura-SSS Hubballi Passenger, 16540 Mangaluru Junction-Yesvantpur Express and 16575 Yesvantpur-Mangaluru Junction Gomateshwara Express.
  • August 3 cancellations included Train 16515 Yesvantpur-Karwar Express, 16576 Mangaluru Junction-Yesvantpur Gomateshwara Express and 16596 Karwar-KSR Bengaluru Panchaganga Express.
  • Train 16596, which began its August 1 journey from Karwar, was diverted through Mangaluru Junction, Shoranur, Erode and Jolarpettai before proceeding towards Bengaluru.
  • Trains linking Bengaluru with coastal Karnataka and Kerala were rerouted through Shoranur, Palakkad, Erode and Jolarpettai. Hubballi-Mangaluru services were sent through Londa, Castle Rock and Madgaon.
  • Seven trains were also short-terminated at Hassan, Sakleshpur, Subrahmanya Road or Kabaka Puttur, including services numbered 16585, 16511, 17377, 16595, 16586, 16512 and 17378.

The New Indian Express train update confirmed the short-termination points and the longer diversion taken by the Panchaganga Express.

Why Is Restoration Taking Longer In The Ghat Section?

The Sakleshpur-Subrahmanya Road line cuts through steep slopes, tunnels, bridges and forested terrain. Road access near several track locations is limited, so machinery, labour and repair material often have to be moved by rail. Continuous rain can also bring fresh soil, loose stones or trees onto an already cleared section.

Railway teams have deployed additional machines and staff, but the line cannot reopen after debris removal alone. Engineers must check whether the formation beneath the track remains stable. Electrical equipment and communication cables also require inspection. This is why officials have avoided giving passengers an exact reopening time.

The disruption also hit around 50 police constable aspirants travelling from Mangaluru to examination centres. Young chess players heading to a national under-11 championship were among those forced to arrange road transport. Hundreds of passengers were stranded overnight, though the railway said refreshments and alternative arrangements were provided at Hassan, Subrahmanya Road and other stations.

What Should Passengers Do Before Starting Their Journey?

Passengers booked on trains crossing Hassan, Sakleshpur or Subrahmanya Road should check the NTES app, railway enquiry number 139, station announcements, and verified South Western Railway social accounts. A train shown as running may still follow a diverted route and arrive several hours late.

Travellers with urgent appointments may consider KSRTC buses or flights where available. Those holding tickets for cancelled services should check their refund status through the original booking channel. Passengers leaving a delayed train midway should first confirm the refund procedure at the station.

Frequently Asked Questions

When Did The Landslip Occur?
It was reported around 8:45 pm on August 1 between Yedakumari and Shrivagilu railway stations.

Which Railway Section Is Affected?
The affected single-line ghat section connects Sakleshpur with Subrahmanya Road on the Bengaluru-Mangaluru rail corridor.

Were Stranded Passengers Helped?
Railway teams arranged refreshments and alternative travel support at selected stations for stranded passengers overnight.

Why Are The Diverted Routes Longer?
Diverted trains avoid Shiradi Ghat by travelling through Kerala or Goa, adding several journey hours.

When Will Normal Services Resume?
Normal operations will resume only after debris removal, track inspection, signalling checks, and safety clearance.